Homebuyers who decide to file a complaint against a builder before the state Real Estate Regulatory Authority often want to know what the process actually involves, not just the legal basis for the claim. This page sets out the process step by step, from identifying the correct Authority to a possible appeal, for a complaint under the Real Estate (Regulation and Development) Act, 2016.
Step 1: Identify the correct state RERA Authority
The complaint is filed with the Real Estate Regulatory Authority of the state in which the project is registered, not the state where the buyer happens to reside, since each state, and in some cases union territory, has established its own Authority under the Act with jurisdiction over projects registered within it.
Step 2: Decide whether to send a notice first
There is no statutory requirement to send a legal notice before filing a complaint under Section 31, but it is generally sensible to do so first, since it creates a clear written record of the demand and sometimes resolves the matter without a formal proceeding. See our page on legal notice to builder for delay in possession for how that step works.
Step 3: Gather the supporting documents
The builder-buyer agreement, payment proof, the project's RERA registration details, any possession offer letter, and prior correspondence or notice already sent are compiled. A detailed checklist of what is needed is set out on our separate documents page for a RERA complaint.
Step 4: Draft the complaint
The complaint sets out the facts in chronological order, identifies the specific provision of the Act relied upon, typically Section 18 for possession delay or refund, and states the relief sought clearly, whether refund with interest, interest alone for the delay period, compensation, or a specific direction to the promoter, in the form prescribed under the relevant state's RERA Rules.
Step 5: File the complaint and pay the fee
The complaint, supporting documents, and the prescribed fee, which varies by state, are filed, increasingly through the Authority's online portal where available, though physical filing remains an option in many states.
Step 6: Notice to the builder and reply
The Authority issues notice to the builder or promoter, who files a written reply, after which both sides may be permitted to file rejoinders or additional documents as directed.
Step 7: Hearing before the Authority
The Authority conducts hearings, which in many states can be attended through video conferencing, and the Act under Section 29(4) sets a target of disposing of complaints within sixty days of filing, though actual timelines depend heavily on the specific Authority's pendency and the complexity of the matter.
Step 8: The Authority's order
The Authority passes a reasoned order either granting or rejecting the relief sought. An order granting refund, interest, or compensation is binding and executable against the builder.
Step 9: Appeal, if necessary
Either side can appeal the Authority's order to the state's Real Estate Appellate Tribunal under Sections 43 and 44 of the Act, generally within sixty days of the order. Where a promoter appeals an order directing payment of refund or interest, Section 43(5) requires the promoter to pre-deposit the amount awarded as a condition of the appeal being entertained, which protects the buyer during the appeal. A further appeal from the Tribunal lies to the High Court, but only on a substantial question of law.
How this works remotely, pan-India
Document gathering and drafting can be done entirely remotely regardless of where the buyer or project is located, filing is increasingly online, and hearings before many state Authorities are at least available through video conferencing, so attendance at every stage does not necessarily require travel to the state where the project is situated, though this varies by state Authority. For representation at hearings specifically, see our page on RERA online and virtual hearing representation.
Frequently asked questions
Frequently asked questions
How long does a RERA complaint typically take from filing to order?
Section 29(4) of the Act sets a target of sixty days for disposal, but actual timelines vary considerably depending on the specific Authority's pendency, whether the builder contests the complaint, and the complexity of the issues raised, so the sixty-day target is not always met in practice.
Do I need to be present in person for the RERA hearing?
Many state Authorities now conduct or at least permit hearings through video conferencing, so personal presence in the state where the project is located is often not strictly necessary, though this depends on the specific Authority's current practice and the stage of the proceeding.
What happens if the builder does not respond to the notice issued by the Authority?
The Authority can proceed to decide the complaint based on the material before it, including the buyer's documents and submissions, even where the builder fails to file a reply or appear, though the specific approach taken varies by Authority and case.
Can I withdraw my RERA complaint if the builder settles with me during the proceeding?
Yes, parties can generally inform the Authority of a settlement reached during the proceeding, and the complaint can then be disposed of on that basis rather than being carried through to a contested order.
This article explains the general legal position for information only. It is not legal advice, and the outcome of any matter depends on its own facts and the rules that apply to it.