Searches such as "step by step process of national highway land acquisition" or "how to challenge NHAI compensation" point to one sequence of stages under the National Highways Act, 1956. Each stage has a different officer, a different time limit and a different thing that can go wrong. This page follows the sequence in order. The legal background is on the main page about compensation and arbitration under the National Highways Act, and the paper needed at each stage is on the documents checklist. Time limits are given only where the Act or a court fixes them. Anything else varies by project and district and is flagged as such.
The sequence at a glance
- Read the notification and identify the law and the project.
- Object within 21 days under Section 3C, if there is a ground.
- Declaration and vesting under Section 3D.
- Public notice and claim under Section 3G.
- The Competent Authority's award under Section 3G(1).
- Deposit, payment and possession under Sections 3H and 3E.
- The decision point: accept the award or seek arbitration.
- Application to the arbitrator under Section 3G(5).
- The arbitration and the award.
- A Section 34 petition and what follows.
Step 1: Read the notification and identify the law
Who acts: the owner and the owner's advocate. What happens: the Section 3A notification is published in the Gazette, with its substance in two local newspapers, one in a vernacular language. The Ministry of Road Transport and Highways uses an online system, Bhoomi Rashi, to prepare draft Section 3A and 3D notifications and to route payments. The first task is to match the village, khasra number and area in the notification with the revenue record, and to confirm that the project is a National Highways Act acquisition. Some state expressways are built on land bought by agreement or acquired under the 2013 Act, and for those the steps differ (see land acquisition compensation in UP). What can go wrong: a mismatch in numbers that is noticed only at the compensation stage. Decision point: whether there is a ground to object.
Step 2: Objections under Section 3C
Who acts: any interested person, before the Competent Authority. Time: 21 days from the Section 3A publication, as fixed by the Act. What happens: a written objection with reasons is filed, the Competent Authority hears the objector in person or through a legal practitioner, and decides by an order that the Act describes as final. The objection is directed at the purpose, the alignment or the description of the land. It is not the place to argue about the amount. What can go wrong: filing after the 21 days, or filing without a stamped copy. Decision point: whether to challenge the order further. A writ petition against the notification is a narrow remedy, and the facts must show something more than disagreement with the alignment.
Step 3: Declaration and vesting under Section 3D
Who acts: the Central Government, on the Competent Authority's report. Time: the Section 3A notification lapses if no Section 3D declaration is published within one year. What happens: on the declaration the land vests absolutely in the Central Government, free from encumbrances. What can go wrong: owners often assume they keep ownership until compensation is paid, but under the Act vesting comes first. Decision point: where the dates suggest the notification lapsed, an advocate can examine whether that ground is available.
Step 4: Public notice and claims under Section 3G
Who acts: the Competent Authority publishes a notice in two local newspapers, one vernacular, and interested persons respond. What happens: the notice describes the land and requires interested persons to appear, in person, through an agent or through a legal practitioner, and state their interests. The owner files a written claim with the title papers, sale deeds of comparable land, the valuation report and details of structures, trees and loss. Section 3G(7) lists what is to be considered: market value on the date of the Section 3A notification, severance, injurious affection and relocation costs. What can go wrong: not appearing, appearing without valuation evidence, or leaving out a co-owner. Time: the notice itself states the date, and it varies by project.
Step 5: The award under Section 3G(1)
Who acts: the Competent Authority. What happens: the compensation is determined by an order. For determinations on or after the 2015 cut-off, the 2013 Act's compensation scheme applies through the 2015 Removal of Difficulties Order, and the Supreme Court in Manav Bhanot v. National Highway Authority of India (8 September 2026) held that it is the date of this determination, not of the arbitral award, that decides whether the 1894 Act or the 2013 Act governs solatium and interest. Where only a right of user or easement is acquired, the amount is 10 percent of the amount determined for the land. What can go wrong: the order is read only for the total. The date, each component and the basis for market value should be noted. Decision point: whether the award reflects the evidence filed.
Step 6: Deposit, payment and possession
Who acts: the Central Government deposits the amount with the Competent Authority under Section 3H(1), and the Competent Authority pays the persons entitled. What happens: after the deposit, the Competent Authority may direct surrender of possession within 60 days under Section 3E, and if there is refusal, seek enforcement through the District Collector. If several persons claim the money, or the share is disputed, the Competent Authority refers that dispute to the principal civil court of original jurisdiction where the land lies under Section 3H(4). What can go wrong: payment delayed by revenue record gaps; a mortgagee or co-owner claiming a share; statements signed at payment that are not read. Time: the 60 days in Section 3E is statutory; payment timing varies by project.
Step 7: The decision point, accept the award or seek arbitration
Receiving the money does not need to be the end of the matter, but it should not be assumed to preserve every right either. This is the stage where the amount is compared with the evidence: sale deeds near the Section 3A date, the circle rate, the valuation and the components of the award. The advocate usually advises on the strength of the case, the cost and time of arbitration, and any limitation question. The Act's text for Section 3G(5) does not itself state a time for applying for arbitration, and delay has been dealt with by courts on the facts, so a decision should not be left to drift.
Step 8: Application for arbitration under Section 3G(5)
Who acts: either party, by applying for the amount to be determined by an arbitrator appointed by the Central Government. What happens: the Central Government notifies arbitrators for districts in the Gazette. The officer notified as arbitrator differs from district to district, so the current notification for the district must be checked. The application sets out the Competent Authority's award, the amount claimed, the grounds and the documents. What can go wrong: applying to the wrong officer after a change in notification; an incomplete application. Time: not stated in Section 3G(5); see Step 7.
Step 9: The arbitration and the award
Who acts: the arbitrator, the claimant, and the project office or NHAI as the other party. What happens: the Arbitration and Conciliation Act, 1996 applies under Section 3G(6), subject to the National Highways Act. There is a statement of claim, a reply, evidence by affidavit and documents (sale deeds, valuation, the structures), hearing and an award with reasons. If the arbitrator awards more than the Competent Authority, Section 3H(5) allows interest at 9 percent a year on the excess from the date of possession until the excess is deposited. The excess and interest are deposited with the Competent Authority for payment. What can go wrong: relying on documents that were never filed; not cross-checking the valuation date against the Section 3A date; not obtaining the signed copy of the award in a way that fixes the date of receipt. Decision point: accept the award or challenge it.
Step 10: Section 34 petition and appeal
Who acts: a party aggrieved by the award, before the court having jurisdiction under the Arbitration Act, ordinarily the principal civil court of original jurisdiction. Time: three months from receipt of the signed award, extendable by 30 days if sufficient cause is shown, and not beyond that. What happens: the petition must fit within the grounds in Section 34. The Supreme Court has held that the court can set an award aside but cannot modify or enhance it (Project Director, NHAI v. M. Hakeem, (2021) 9 SCC 1) and that patent illegality does not allow re-appreciation of evidence (Ssangyong Engineering and Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131). An order on the petition can be taken in appeal under Section 37 of the Arbitration Act, ordinarily to the High Court, and the Supreme Court can be approached after that in the manner the Constitution allows. What can go wrong: counting the time from the wrong date; asking the court for a higher valuation, which a Section 34 court cannot give.
A parallel track: solatium and interest on older awards
Where the Section 3G(1) determination was before 1 January 2015, the issue is usually solatium and interest under Union of India v. Tarsem Singh, (2019) 9 SCC 304. After the Court's orders of 4 February 2025 and 25 March 2026, the entitlement is described as undisputed, with separate directions for delayed and closed claims depending on the date the claim was first raised. The forum for a particular old claim depends on its history, so the dated order and claim papers should be reviewed.
Where the framework itself is under challenge
The Punjab and Haryana High Court declared Sections 3G and 3J void on 20 March 2025, the Supreme Court stayed that judgment on 30 May 2025, and on 13 January 2026 the Court noted that the challenge to those sections remained pending and revived Section 34 petitions that had been withdrawn after the High Court ruling. Until a final decision or an amendment, the statutory sequence above applies.
Common mistakes across the process
- Treating the Section 3C hearing as the stage to argue the amount.
- Leaving evidence for a later stage, when the arbitrator decides on what is placed before the arbitrator.
- Mixing up the dates: the Section 3A date (market value), the Section 3G(1) order date (which regime) and the date of receipt of the signed award (Section 34).
Frequently asked questions
What is the step by step process of national highway land acquisition?
A Section 3A notification, objections within 21 days under Section 3C, a Section 3D declaration that vests the land, a Section 3G public notice and claim, the Competent Authority's award under Section 3G(1), deposit and payment under Section 3H, and possession under Section 3E. If the amount is not accepted, an arbitrator is appointed under Section 3G(5), and the award can be challenged under Section 34 of the Arbitration and Conciliation Act.
How do I challenge NHAI compensation if I think it is too low?
By applying for arbitration under Section 3G(5) with valuation and comparable sale deed evidence. The arbitrator decides the amount, and a later Section 34 petition is limited to the statutory grounds.
How many days do I have to object to a national highway land acquisition notification?
21 days from the publication of the Section 3A notification, under Section 3C.
Who is the arbitrator for national highway compensation in my district?
The Central Government notifies an arbitrator for each district in the Gazette. The officer differs between districts and notifications are replaced from time to time, so the current notification for the district should be checked.
Can the court increase compensation in a Section 34 petition?
No. The Supreme Court held in M. Hakeem (2021) that a Section 34 court can set an award aside but cannot modify it, so the valuation case must be made before the Competent Authority and the arbitrator.
What happens if possession is taken before I receive the money?
Under Section 3E possession follows the deposit of compensation, and if the amount determined by the arbitrator is higher, Section 3H(5) provides for interest at 9 percent a year on the excess from the date of possession until it is deposited.
Does the Supreme Court's stay of the High Court judgment on Sections 3G and 3J affect my case?
The stay means the High Court ruling declaring those sections void is not in operation, and the statutory process continues to be followed. The Supreme Court is yet to decide the question finally, so the position should be checked when a matter is live.
This article explains the general legal position for information only. It is not legal advice, and the outcome of any matter depends on its own facts and the rules that apply to it.