Construction and EPC contract review before signing: what owners and contractors should check, clause by clause

यह जानकारी हिंदी में पढ़ें

Construction and EPC contract review is a clause-by-clause legal reading of a building, civil works or engineering, procurement and construction (EPC) contract before it is signed, so that the owner or the contractor knows what risk it is accepting on scope, price, time, quality and payment. The review checks whether the contract says what the parties have actually agreed commercially, whether its risk clauses (liquidated damages, bank guarantees, retention, defects liability, termination) are workable and enforceable under Indian law, and whether the dispute resolution clause will function if things go wrong. The review is done remotely: the draft is sent by e-mail, comments and a redline come back, and points are discussed on a video call, for businesses anywhere in India.

What a construction or EPC contract is, and when review is advisable

A construction contract is an agreement under which one party (the contractor) builds or installs something for another (the owner or employer) for a price. The common forms in India are item-rate contracts, where the contractor is paid for measured quantities at the rates in a bill of quantities (BOQ); lump-sum contracts, where a fixed price covers a defined scope; and EPC or turnkey contracts, where a single contractor takes responsibility for design, procurement of equipment and materials, construction and commissioning, usually for a fixed price and a fixed completion date. Private contracts often borrow from international standard forms such as the FIDIC forms; government departments use their own general conditions.

Review is advisable whenever a business is about to sign, renew or substantially amend such a contract, and especially when:

  • the contractor has received the owner's standard form and is expected to accept it with few changes;
  • the owner is about to sign a contractor's draft that was prepared with the contractor's interests in mind;
  • the contract value is large relative to the business, or the contract requires bank guarantees, mobilisation advances or personal guarantees;
  • the contract will be passed down "back to back" to subcontractors, so that the main contractor's risk must match what it can recover from others;
  • the project is time-critical, with a planned opening date.

Where the business has no draft yet and needs one prepared, that is drafting work; see the page on commercial contract drafting. This page is about reviewing a contract the business has received or already uses.

The legal framework that governs the review

There is no single construction statute in India. Private construction contracts are governed mainly by the Indian Contract Act, 1872, read with the specific terms the parties sign. The provisions that matter most in a review are these:

  • Sections 10 and 23, Contract Act: an agreement is a contract if made by free consent of competent parties for a lawful consideration and object; terms opposed to public policy are void.
  • Section 28, Contract Act: a clause that absolutely restricts a party from enforcing its rights through legal proceedings, or limits the time within which it may do so, is void to that extent. Short claim-notice clauses need to be read with this provision.
  • Sections 53 and 55, Contract Act: where one party prevents the other from performing, the party prevented may treat the contract as voidable and claim compensation for its loss; where time is of the essence and performance is delayed, the contract becomes voidable at the option of the promisee, and where time is not of the essence, the promisee may claim compensation for delay.
  • Sections 73 and 74, Contract Act: compensation for breach, and the treatment of sums named in the contract as payable on breach. In ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705, the Supreme Court upheld a pre-estimated liquidated damages clause in a supply contract. In Kailash Nath Associates v. Delhi Development Authority (2015) 4 SCC 136, the Court held that under Section 74 only reasonable compensation can be awarded, with the named sum as the upper limit, and that where loss is capable of proof, damage or loss is a condition for the award.
  • Bank guarantees: a performance or advance bank guarantee is an independent contract between the bank and the beneficiary. In U.P. Cooperative Federation Ltd. v. Singh Consultants and Engineers (P) Ltd. (1988) 1 SCC 174, the Supreme Court held that courts should not restrain encashment of an unconditional guarantee except in cases of fraud of the kind that vitiates the transaction. U.P. State Sugar Corporation v. Sumac International Ltd. (1997) 1 SCC 568 recognised irretrievable injustice as the second narrow exception. Hindustan Construction Co. Ltd. v. State of Bihar (1999) 8 SCC 436 held that a guarantee must be invoked strictly in accordance with its own terms.
  • Arbitration and Conciliation Act, 1996: Section 7 requires the arbitration agreement to be in writing. Section 12(5) and the Seventh Schedule make certain persons connected with a party ineligible to act as arbitrators. In Central Organisation for Railway Electrification v. ECI-SPIC-SMO-MCML (JV), decided on 8 November 2024, a Constitution Bench held that clauses allowing one interested party to unilaterally appoint a sole arbitrator, or to curate a panel from which the other side must choose, offend the principle of equal treatment; the Court applied its ruling prospectively, to arbitrator appointments made after the judgment.
  • MSMED Act, 2006: where the contractor or supplier is a micro or small enterprise registered as such when the contract is made, the buyer must pay within the agreed period, which cannot exceed forty-five days from acceptance or deemed acceptance (or within fifteen days where no period is agreed), failing which compound interest at three times the bank rate notified by the Reserve Bank applies. Disputes can go to the Micro and Small Enterprises Facilitation Council under Section 18, and in Gujarat State Civil Supplies Corporation Ltd. v. Mahakali Foods (P) Ltd., decided on 31 October 2022, the Supreme Court held that this statutory route overrides a private arbitration agreement. Registration obtained after the contract operates only for later supplies. See MSME Samadhaan and delayed payment claims.
  • Specific Relief Act, 1963: Section 20A, inserted in 2018, bars courts from granting an injunction in a suit involving a contract relating to an infrastructure project specified in the Schedule to the Act where the injunction would impede or delay the project. Whether a given project falls in the Schedule has to be checked against the current Schedule.
  • Labour law: the four Labour Codes came into force on 21 November 2025. The Occupational Safety, Health and Working Conditions Code, 2020 replaced the Contract Labour (Regulation and Abolition) Act, 1970 and the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996, and the Code on Social Security, 2020 replaced the Building and Other Construction Workers' Welfare Cess Act, 1996. Rules are being notified state by state, so the compliance clause should refer to the Codes and current state rules, not the repealed Acts.
  • Government contracts: contracts with the Union or a State must satisfy Article 299 of the Constitution, and are usually on the department's general conditions. See government contract and work order review.

The price clause should also state whether rates include GST and who bears a change in the GST rate.

Clause-by-clause review guide

1. Parties, contract documents and order of precedence

The review confirms the exact legal names of the parties, the authority of the signatory, and the list of documents that form the contract: agreement, letter of acceptance, general and special conditions, specifications, drawings, BOQ, tender clarifications and minutes of negotiation. A risky drafting example: "The contract comprises all documents exchanged between the parties." This invites disputes over which e-mail or minute governs. A better approach lists each document by title and date and states which prevails if they conflict.

2. Scope of work, BOQ and drawings

The review checks whether the scope is defined by reference to specific drawings and specifications, whether items such as temporary works, approvals, utilities, testing and as-built drawings are inside or outside the price, and whether the BOQ has gaps. In an EPC contract, phrases such as "all works necessary for completion whether or not shown in the drawings" place design and quantity risk on the contractor; that risk should be reflected in the price.

3. Price, measurement and escalation

The review checks the price basis (item rate, lump sum or cost plus), the method of measurement, and whether a price variation formula applies to steel, cement, fuel or labour. A firm-price clause over a long project shifts all inflation risk to the contractor. Where escalation is agreed, the base date, indices and cap should be stated clearly.

4. Variations and change orders

A risky clause allows unlimited variations at rates "decided by the engineer". The review looks for a written change order procedure, a limit beyond which new rates are negotiated, a rule for valuing work not covered by BOQ rates, and the effect of a variation on time.

5. Time, programme and extension of time

The review checks the start date (often linked to site handover, drawings or advance payment), milestones, the completion date, and the grounds and procedure for extension of time. Delays caused by the owner, such as late drawings, late payments or late site access, should entitle the contractor to more time and, where agreed, cost.

6. Liquidated damages

Given Kailash Nath, a liquidated damages clause is easier to apply when the rate is a genuine pre-estimate of loss, is stated per week or per day of delay, and is capped (commonly as a percentage of contract value, as the parties agree). Stacking liquidated damages, general damages and a "penalty" for the same delay invites challenge. The review also checks whether they are the exclusive remedy for delay.

7. Performance security, advance guarantees and the guarantee format

The review reads the annexed guarantee format word by word: amount, validity, claim period, whether it is "unconditional and irrevocable", whether invocation requires a statement of breach, and how it reduces as work progresses. It also checks when the owner must return the guarantee after completion or defects liability.

8. Payment, certification and retention money

Points checked include the interim payment cycle, the time for certification and payment, deductions, the rate and cap of retention money, when retention is released (for example half on completion and half after defects liability), and whether retention can be replaced by a bank guarantee. A clause allowing the owner to "withhold any amount it considers appropriate" should be narrowed to stated grounds.

9. Defects liability and warranties

The defects liability period, the procedure for notifying defects, the contractor's right to remedy them first, and how equipment warranties from manufacturers pass to the owner are checked.

10. Site, approvals, safety and labour compliance

The review allocates responsibility for site conditions, statutory approvals, safety, insurance of workers, labour registration and welfare cess under the Labour Codes, and indemnities for labour claims.

11. Insurance, indemnity and limitation of liability

Contractor's all-risk insurance, third-party liability and workmen's compensation cover, the named insured, and an overall liability cap with carve-outs (for example for fraud and wilful misconduct) are checked. See limitation of liability and indemnity clause review.

12. Suspension, termination and force majeure

The review checks termination for default (with notice and cure period), termination for convenience (and what is paid), the contractor's right to suspend for non-payment, and the force majeure definition, notice and consequences.

13. Dispute resolution

The tiered steps (engineer's decision, negotiation, mediation, arbitration), the seat and venue, the number of arbitrators and the appointment method are reviewed in the light of the 2024 Constitution Bench ruling and the MSMED Act. See commercial arbitration clause drafting.

Stamp duty and execution

Stamp duty on construction agreements, bank guarantees and indemnity bonds is charged under the Indian Stamp Act, 1899 as adopted by a state or under the state's own stamp law (Maharashtra, Karnataka, Gujarat and Tamil Nadu, for instance, have their own enactments or schedules), so the duty and the instrument description vary by state and must be checked at the time of execution. An unstamped or under-stamped document may face admissibility objections until duty and penalty are paid. On 13 December 2023 a seven-judge bench of the Supreme Court held that such an agreement is inadmissible in evidence but not void, and that an arbitration clause in it remains enforceable, the stamping objection being for the arbitral tribunal. Construction contracts are not ordinarily compulsorily registrable, but a contract that also creates a lease or other interest in land may attract the Registration Act, 1908. Execution points include signing by authorised signatories, a board resolution or power of attorney where needed, initialled annexures, and electronic signatures where permitted under the Information Technology Act, 2000.

What the review output looks like

Depending on what the business needs, the output is one or more of: a comments version of the draft; a tracked-changes redline with proposed wording; an issues list that ranks points as essential, desirable or acceptable as drafted, with a short reason for each; and a short note summarising the main risks in plain language for the decision-maker.

Limits of a review

A review explains legal risk in the document and proposes wording. It does not guarantee that the other side will accept the changes, that the project will run without disputes, or that a court or arbitral tribunal will read a clause the same way. It does not replace technical, tax or insurance advice.

Common mistakes when signing without review

  • Signing the letter of acceptance first and treating the formal contract as a formality, when the acceptance may already conclude the contract.
  • Agreeing to an EPC price without checking which design and quantity risks it covers.
  • Accepting a bank guarantee format with no expiry or claim period.
  • Missing short notice periods for extension of time and variation claims.
  • Passing risk down to subcontractors on different terms from the main contract, leaving the main contractor exposed in the gap.
  • Citing repealed labour Acts in the compliance clause after the Labour Codes came into force.

Illustrative scenarios

Pune: a mid-sized civil contractor receives an owner's EPC draft for a warehouse with a firm price, a broad "all works necessary" scope and an unconditional performance guarantee with no expiry. The review focuses on design risk, escalation, the guarantee format and the extension of time procedure.

Hyderabad: a hospital trust is about to sign a contractor's draft for a new block. The owner-side review checks the completion date, liquidated damages, defects liability and equipment warranties.

Kolkata: a registered small enterprise is offered a back-to-back subcontract for electrical works on a commercial project. The review compares the subcontract with the main contract terms and checks payment timelines in light of the MSMED Act.

Reviewing a construction contract for a business in another city

Because the contract is a document, review does not depend on where the project is. The draft and annexures are shared by e-mail, questions are clarified on a video call, and the redline and note come back by e-mail. Where state law matters, such as stamp duty or local labour rules, the position in the project's state is checked separately. Where the matter later turns into a dispute with a government department, a separate page covers government tender disputes and blacklisting challenges.

Frequently asked questions

What should be checked in a construction contract before signing?

The main points are the contract documents and order of precedence, the scope and BOQ, the price basis and escalation, variations, time and extension of time, liquidated damages, the bank guarantee format, payment and retention, defects liability, insurance and indemnity, termination, force majeure and the dispute resolution clause.

Are liquidated damages in a construction contract enforceable in India?

A liquidated damages clause is read with Section 74 of the Indian Contract Act. Following Kailash Nath Associates v. DDA (2015), only reasonable compensation up to the stated sum can be awarded, and where loss can be proved, proof of loss matters. A clause framed as a genuine pre-estimate and capped is easier to apply.

Can the owner invoke a performance bank guarantee while a dispute is pending?

An unconditional bank guarantee is an independent contract, and courts ordinarily do not stop its encashment except for fraud of an egregious kind or irretrievable injustice. Invocation must still follow the terms of the guarantee itself, which is why the guarantee format deserves close review before signing.

What is the difference between an EPC contract and an item-rate contract?

In an item-rate contract the contractor is paid for measured quantities at agreed rates, so quantity risk largely stays with the owner. In an EPC or turnkey contract one contractor designs, procures and builds for a fixed price and date, so more design and quantity risk moves to the contractor.

Who bears the risk of delay caused by the owner?

Under Section 53 of the Contract Act, where one party prevents the other from performing, the party prevented may treat the contract as voidable and claim compensation for its loss. A well-drafted contract lists owner-caused delays as grounds for extension of time and, where agreed, cost. Contractors should comply with the notice procedure the contract sets.

Does an MSME contractor have special payment rights?

A micro or small enterprise registered when the contract is made can rely on the MSMED Act: payment within the agreed period not exceeding forty-five days from acceptance, interest on delay, and reference of disputes to the Facilitation Council, which the Supreme Court has held overrides a private arbitration clause.

Is stamp duty payable on a construction agreement?

Yes, stamp duty is generally payable on the agreement and on related bank guarantees and indemnity bonds, but the amount and the applicable article differ from state to state. The current schedule in the state of execution should be checked at the time of signing.

Can an arbitration clause let one party appoint the arbitrator?

On 8 November 2024 a Constitution Bench of the Supreme Court held that clauses allowing one interested party to unilaterally appoint a sole arbitrator, or to force the other side to choose from a curated panel, breach equal treatment. The ruling applies to arbitrator appointments made after that date, so clauses in new contracts should provide a balanced appointment method.

Can a construction contract be reviewed remotely for a business in another city or state?

Yes. The draft and annexures are sent by e-mail, questions are discussed on a video call, and comments, a redline or a short note are returned by e-mail. State-specific points such as stamp duty and labour rules are checked for the state where the project is located.

This article explains the general legal position for information only. It is not legal advice, and the outcome of any matter depends on its own facts and the rules that apply to it.

Related: Documents needed for construction and EPC contract review. Construction and EPC contract review, step by step. Government tender disputes and blacklisting challenges. Commercial arbitration clause drafting. MSME Samadhaan and delayed payment claims. Government contract and work order review.