A construction or EPC contract review usually moves through eleven stages: intake and conflict check, understanding the commercial intent, a first full read, an issues list, a redline, discussion with the business, negotiation rounds with the other side, a final check of the agreed text, execution, stamping and any registration, and finally storing the contract and diarising its key dates. Not every engagement needs every stage; a short work order may need only a first read and a note. The stages below explain who acts at each step, the decisions the business has to make, and what commonly goes wrong. The whole process can be run remotely by e-mail and video call for a business anywhere in India.
Stage 1: Intake and conflict check
Who acts: the advocate, with the person instructing on behalf of the business.
The business shares the draft and basic details: the parties, the project, its location and the planned signing date. Before reading the draft in depth, the advocate checks that there is no conflict of interest with the other party and confirms who will give instructions and receive advice. Confidentiality of the documents is agreed.
What can go wrong: instructions come from several people in the business with different priorities, or the other party's correct legal name is not known until later.
Stage 2: Understanding the commercial intent
Who acts: the business's commercial or project head, with the advocate.
A short call establishes which side the business is on (owner, main contractor or subcontractor), what has already been agreed, which terms are fixed by a tender and cannot be changed, and what matters most: price certainty, cash flow, completion date, limiting guarantee exposure, or keeping the relationship smooth. The documents listed in the checklist are collected at this stage.
Decision point: whether the review is a full redline or a focused note on the highest-risk clauses. In government tenders where the conditions are non-negotiable, a note on risks and compliance steps is often more useful than a redline.
Stage 3: First full read
Who acts: the advocate.
The whole contract is read with its annexures, not only the agreement form. The reviewer maps the order of precedence between documents, the definitions, and how the clauses on time, payment, guarantees and termination connect. Cross-references are checked, because a clause that refers to the wrong clause number can change its meaning. Applicable law is checked as needed, for example Sections 73 and 74 of the Indian Contract Act, 1872 on damages, the MSMED Act, 2006 on payment, and the Labour Codes in force since 21 November 2025 for compliance clauses.
What can go wrong: an annexure that the draft relies on is missing, or the general conditions are an older edition from the one the business saw at tender stage.
Stage 4: Issues list
Who acts: the advocate.
The issues are listed clause by clause and ranked, for example as essential, desirable, or acceptable as drafted. Each entry states the clause, the risk in plain words, and the proposed change. An issues list lets the business see the whole picture before any text is changed and decide which points to raise.
What can go wrong: the list grows so long that the important points are lost among minor drafting comments. Ranking the issues, and keeping language and formatting corrections separate from risk points, keeps the discussion focused.
Stage 5: Redline
Who acts: the advocate.
The proposed changes are made in tracked changes on an editable copy, with short comments explaining the reason where the other side may need it. Typical redlines in construction contracts include a cap on liquidated damages, a clear extension of time procedure for owner-caused delay, an expiry date and claim period in the guarantee format, defined grounds for withholding payments, a release schedule for retention money, and a balanced method of appointing arbitrators.
What can go wrong: changes are made on an old version, or the other side's own last changes were not shown as tracked changes, so they are missed.
Stage 6: Discussion with the business
Who acts: the business's decision-maker, with the advocate.
The issues list and redline are discussed on a call. The business decides which points to send, which to hold back as fallback positions, and which to accept. These are commercial decisions for the business; the review explains the legal effect of each choice.
Decision point: whether to send the redline directly to the other side or to raise points first in a meeting. Where the relationship matters, a short covering note explaining the main changes often makes the first round easier.
Stage 7: Negotiation rounds
Who acts: the business, often with the advocate's support on the drafting.
The other side responds by accepting, rejecting or counter-proposing. Each round produces a new version, which should be numbered and dated. Under Section 7 of the Contract Act, an acceptance must be absolute and unqualified, so a reply that accepts "subject to" changes is in law a counter-proposal. Agreed points are written into the draft rather than left in e-mails.
What can go wrong: work starts on site while negotiation continues, so that the parties later disagree on which version, if any, governs. Where work must start early, a short interim letter recording the key terms is safer than no document.
Stage 8: Final check
Who acts: the advocate.
The clean execution copy is compared with the last agreed redline. Party names, addresses, amounts in words and figures, dates, milestone tables, the guarantee format, annexure numbering and signature blocks are checked. Points that were agreed in principle but never drafted are identified.
What can go wrong: the "final" copy prepared by the other side contains changes that were never shown as tracked changes.
Stage 9: Execution
Who acts: the authorised signatories of both parties.
The contract is signed by persons with authority, supported by a board resolution or power of attorney where needed. Annexures are initialled. Electronic signatures can be used where the Information Technology Act, 2000 permits, though some departments and banks still require physical signatures. The date of execution is recorded.
What can go wrong: the person who signs for a company or firm has authority to bid but not to sign the contract or furnish guarantees, or the two parties sign different copies. Each party should keep a fully signed counterpart with all annexures attached.
Stage 10: Stamping and registration
Who acts: the business, usually with the advocate's guidance.
Stamp duty on the agreement, and separately on bank guarantees and indemnity bonds, is paid under the stamp law of the state concerned. Rates, the applicable article and the time for payment vary by state, and many states use e-stamping; the current position in the state of execution should be confirmed. An under-stamped document may face objections when it has to be produced as evidence. Construction contracts are not ordinarily compulsorily registrable, but a contract that also creates an interest in land may need registration under the Registration Act, 1908.
Stage 11: Storing the contract and diarising dates
Who acts: the business's project and accounts teams.
The signed and stamped original is stored safely, with scanned copies for the site and accounts teams. Key dates are diarised: milestones, notice periods for extension of time and variation claims, guarantee expiry and renewal dates, the end of the defects liability period, and retention release dates. The limitation period for a claim for breach of contract is generally three years under the Limitation Act, 1963, but the facts, the arbitration clause and later acknowledgements can affect how it runs, so the position should be checked when a dispute arises.
What can go wrong: a performance guarantee expires during an extended project and the owner invokes it for non-renewal; a contractor misses a short notice period because the site team never saw the clause.
For the clause-by-clause guide, see construction and EPC contract review. For contracts with government departments, see also government contract and work order review.
Frequently asked questions
How do you review a construction contract step by step?
Collect the full draft and related papers, understand the commercial intent, read the whole contract with annexures, prepare a ranked issues list, redline the draft, agree priorities with the business, negotiate, check the final copy, execute, stamp, and diarise key dates.
Should work start on site before the contract is signed?
It is better avoided. If work must start, a short interim letter recording the key terms, the scope and the basis of payment reduces the risk of a later dispute over which terms apply.
What is an issues list in contract review?
It is a table of the clauses that need attention, each with the risk in plain words, a proposed change, and a priority such as essential, desirable or acceptable as drafted. It helps the business decide what to negotiate.
Is a reply accepting the contract with changes a binding acceptance?
Under Section 7 of the Indian Contract Act, acceptance must be absolute and unqualified. A reply that accepts subject to changes is generally treated as a counter-proposal, which the other side may accept or reject.
Can a construction contract be signed electronically?
Electronic signatures are recognised under the Information Technology Act, 2000, subject to its exclusions. In practice some owners, departments and banks still require physical signatures and stamped paper, so the requirement should be confirmed with the other side.
Which dates should be diarised after signing?
Milestones, the completion date, notice periods for extension of time and variation claims, bank guarantee expiry and renewal dates, the end of the defects liability period, retention release dates, and the limitation period for any claim.
Can the whole review process be handled remotely?
Yes. Documents are exchanged by e-mail, discussions take place on video calls, and redlines and notes are returned electronically, for a business or project in any state. Stamping is done in the state of execution.
This article explains the general legal position for information only. It is not legal advice, and the outcome of any matter depends on its own facts and the rules that apply to it.